Drilling Operations Management

Project management, crew operations, equipment maintenance, and documentation for drilling programs.

Project Planning

Pre-Drilling Phase

  • Site investigation: Geophysical surveys, test holes, water quality baseline — budget 10-15% of total project cost
  • Well design: Diameter, depth, casing program, screen specs, pump requirements
  • Permits: Drill permit, water rights, environmental clearances — allow 2-12 weeks lead time
  • Access: Road construction, pad preparation, utility locations (call before you dig)
  • Budget: Include 15-20% contingency for unexpected conditions

Drilling Phase

  • Mobilization: Rig transport, setup, and safety inspection — typically 1-2 days
  • Drilling rate: Track daily progress — compare to geological predictions
  • Sampling: Collect rock/soil samples at regular intervals — document formations
  • Casing installation: Install as drilling progresses — grout immediately
  • Drilling fluids: Monitor and maintain mud properties — adjust as formations change

Completion Phase

  • Screen installation: Based on formation analysis — correct slot size for aquifer grain size
  • Grouting: Sanitary seal from surface to screen — prevent surface contamination
  • Development: Surge, airlift, or overpump to remove fines and develop well
  • Pump installation: Set pump at correct depth, install pitless adapter, connect electrical
  • Testing: Pump test (24-72 hours) — determine sustainable yield and water quality

Crew Management

Team Structure

  • Driller/foreman: Overall responsibility — makes operational decisions, manages safety
  • Assistant driller: Operates rig controls, monitors drilling parameters
  • Roughneck/helper: Pipe handling, mixing fluids, general labor
  • Water hauler: Delivers water for mud mixing, manages water supply

Shift Operations

  • Shift length: 8-12 hours typical — 12-hour shifts common for remote operations
  • Handover: Formal shift changeover — report drilling progress, issues, pending tasks
  • Tailgate talks: 5-10 minute safety briefing before each shift
  • Communication: Radio or cell phone — maintain contact with site supervisor
ActivityFrequencyResponsibleDocumentation
Pre-shift inspectionEvery shiftDrillerInspection checklist
Safety meetingDailyForemanMeeting minutes
Equipment checkDailyAssistant drillerMaintenance log
Drilling reportDailyDrillerDaily drilling report
Fluid testingEvery 4 hoursAssistant drillerMud log
Gas monitoringContinuousAll crewGas detector log

Equipment Maintenance

Preventive Maintenance Schedule

  • Daily: Engine oil level, hydraulic fluid, coolant, belt tension, air filter, grease fittings
  • Weekly: Hydraulic filter, drill pipe inspection, rotary table, mud pump bearings
  • Monthly: Engine oil and filter, hydraulic fluid analysis, wire rope inspection
  • Annually: Complete engine overhaul, pressure testing, NDT of critical components

Consumables Management

  • Drill bit tracking: Record footage per bit — optimize bit selection and replacement timing
  • Mud additives: Maintain 2-week supply minimum — track consumption rates
  • Casing inventory: Pre-order based on well design — allow 1-2 weeks delivery
  • Fuel: Daily consumption tracking — ensure 3-day reserve minimum

Documentation & Reporting

  • Daily drilling report: Footage drilled, formations encountered, bit changes, problems, chemicals used
  • Mud log: Drilling fluid properties: weight, viscosity, pH, sand content, filtrate loss
  • Geological log: Formation descriptions, sample descriptions, water strikes
  • Construction report: As-built details: depths, casing, screen, grouting, development
  • Pump test report: Test data, yield calculation, specific capacity, water quality
  • Photographic record: Daily photos of progress, key activities, problems encountered
💧
Key Performance Indicators (KPIs)

1) Drilling rate (m/hour) — target vs actual. 2) Bit life (m/bit) — optimize bit selection. 3) Non-productive time (NPT) — target <10%. 4) Safety incidents — target zero. 5) Cost per meter — track vs budget. 6) Water quality compliance — 100%.

Communication Protocols

  • Daily standup: Morning meeting — review yesterday, plan today, identify risks
  • Incident reporting: Immediate notification for safety events, environmental spills, equipment damage
  • Stakeholder updates: Weekly progress report to client/owner — written + verbal
  • Regulatory notification: Report to authorities as required — drilling start, completion, water quality