Drilling Operations Management
Project management, crew operations, equipment maintenance, and documentation for drilling programs.
Project Planning
Pre-Drilling Phase
- Site investigation: Geophysical surveys, test holes, water quality baseline — budget 10-15% of total project cost
- Well design: Diameter, depth, casing program, screen specs, pump requirements
- Permits: Drill permit, water rights, environmental clearances — allow 2-12 weeks lead time
- Access: Road construction, pad preparation, utility locations (call before you dig)
- Budget: Include 15-20% contingency for unexpected conditions
Drilling Phase
- Mobilization: Rig transport, setup, and safety inspection — typically 1-2 days
- Drilling rate: Track daily progress — compare to geological predictions
- Sampling: Collect rock/soil samples at regular intervals — document formations
- Casing installation: Install as drilling progresses — grout immediately
- Drilling fluids: Monitor and maintain mud properties — adjust as formations change
Completion Phase
- Screen installation: Based on formation analysis — correct slot size for aquifer grain size
- Grouting: Sanitary seal from surface to screen — prevent surface contamination
- Development: Surge, airlift, or overpump to remove fines and develop well
- Pump installation: Set pump at correct depth, install pitless adapter, connect electrical
- Testing: Pump test (24-72 hours) — determine sustainable yield and water quality
Crew Management
Team Structure
- Driller/foreman: Overall responsibility — makes operational decisions, manages safety
- Assistant driller: Operates rig controls, monitors drilling parameters
- Roughneck/helper: Pipe handling, mixing fluids, general labor
- Water hauler: Delivers water for mud mixing, manages water supply
Shift Operations
- Shift length: 8-12 hours typical — 12-hour shifts common for remote operations
- Handover: Formal shift changeover — report drilling progress, issues, pending tasks
- Tailgate talks: 5-10 minute safety briefing before each shift
- Communication: Radio or cell phone — maintain contact with site supervisor
| Activity | Frequency | Responsible | Documentation |
|---|---|---|---|
| Pre-shift inspection | Every shift | Driller | Inspection checklist |
| Safety meeting | Daily | Foreman | Meeting minutes |
| Equipment check | Daily | Assistant driller | Maintenance log |
| Drilling report | Daily | Driller | Daily drilling report |
| Fluid testing | Every 4 hours | Assistant driller | Mud log |
| Gas monitoring | Continuous | All crew | Gas detector log |
Equipment Maintenance
Preventive Maintenance Schedule
- Daily: Engine oil level, hydraulic fluid, coolant, belt tension, air filter, grease fittings
- Weekly: Hydraulic filter, drill pipe inspection, rotary table, mud pump bearings
- Monthly: Engine oil and filter, hydraulic fluid analysis, wire rope inspection
- Annually: Complete engine overhaul, pressure testing, NDT of critical components
Consumables Management
- Drill bit tracking: Record footage per bit — optimize bit selection and replacement timing
- Mud additives: Maintain 2-week supply minimum — track consumption rates
- Casing inventory: Pre-order based on well design — allow 1-2 weeks delivery
- Fuel: Daily consumption tracking — ensure 3-day reserve minimum
Documentation & Reporting
- Daily drilling report: Footage drilled, formations encountered, bit changes, problems, chemicals used
- Mud log: Drilling fluid properties: weight, viscosity, pH, sand content, filtrate loss
- Geological log: Formation descriptions, sample descriptions, water strikes
- Construction report: As-built details: depths, casing, screen, grouting, development
- Pump test report: Test data, yield calculation, specific capacity, water quality
- Photographic record: Daily photos of progress, key activities, problems encountered
Key Performance Indicators (KPIs)
1) Drilling rate (m/hour) — target vs actual. 2) Bit life (m/bit) — optimize bit selection. 3) Non-productive time (NPT) — target <10%. 4) Safety incidents — target zero. 5) Cost per meter — track vs budget. 6) Water quality compliance — 100%.
Communication Protocols
- Daily standup: Morning meeting — review yesterday, plan today, identify risks
- Incident reporting: Immediate notification for safety events, environmental spills, equipment damage
- Stakeholder updates: Weekly progress report to client/owner — written + verbal
- Regulatory notification: Report to authorities as required — drilling start, completion, water quality